The Transmission Company of Nigeria (TCN) says the Aba–Itu 132 Kilo Volt (kV) transmission line has been successfully restored at 7:53 p.m. on Nov. 8.
The company in a statement in Abuja on Monday, said that the outage, which commenced at 1:02 p.m. on Nov. 7, was caused by a fault on the transmission line.
It explained that the TCN maintenance crew subsequently patrolled the line and carried out the necessary corrective measures, leading to its successful restoration.
Start tomorrow informed
Save your place for the morning brief. We’ll start emailing when delivery goes live.
Free. Confirm by email. Unsubscribe anytime.
”Following the restoration, Port Harcourt Electricity Distribution Company (PHEDC) has resumed the off-take of electricity for onward distribution to customers in Uyo, Eket, Ekim and Itu.”
The company, however, assured electricity consumers of its continued commitment to the efficient transmission of bulk electricity.