HomeEnergyFG expands Gombe transmission capacity to 600MVA
Nov 20, 20262 min read

FG expands Gombe transmission capacity to 600MVA

FG expands Gombe transmission capacity to 600MVA
Galaxy TV · Energy desk · Lagos

The Federal Government has doubled electricity transmission capacity in Gombe State to 600MVA and commissioned a new 120MVA substation in Billiri to improve power supply and support economic activities in the North-East. Inaugurating the projects—including two new transformers at the Gombe Transmission Substation—Minister of Power Joseph Tegbe said the investments will expand electricity access, support local businesses, and attract new investment to benefiting communities.

Story reading is not supported in this browser.

Share

The Federal Government has doubled electricity transmission capacity in Gombe State to 600MVA and commissioned a new 120MVA substation in Billiri as part of efforts to improve power supply and support economic activities in the North-East.

The Minister of Power, Joseph Tegbe, inaugurated the projects, including two new transformers at the Gombe Transmission Substation, saying the investments would expand electricity access, encourage businesses and attract investment to the benefiting communities.

The new Billiri substation has an installed capacity of 120MVA, comprising two 60MVA transformers connected to the existing Gombe–Zabana–Yola transmission line.

Start tomorrow informed

Save your place for the morning brief. We’ll start emailing when delivery goes live.

Free. Confirm by email. Unsubscribe anytime.

Tegbe said the facility was designed to address longstanding electricity infrastructure challenges affecting Billiri, Numan and neighbouring communities.

He explained that improved electricity supply would strengthen local businesses, create employment opportunities and unlock the economic potential of the communities.

The minister described the projects as part of President Bola Tinubu's commitment to expanding critical electricity infrastructure and ensuring that communities were not denied economic opportunities because of inadequate power supply.

The Billiri facility is expected to strengthen electricity supply within the Jos Electricity Distribution Company franchise area.

At the Gombe Transmission Substation, the government also commissioned an additional 300MVA, 330/132kV transformer, increasing transmission capacity at the 330kV level from 300MVA to 600MVA.

The upgrade also involved replacing an existing 30MVA transformer with a 100MVA, 132/33kV unit, increasing downstream transformation capacity to 220MVA, equivalent to 176 megawatts.

The Federal Government said the improvements were expected to enhance electricity supply to more than 70,000 additional households in Gombe and neighbouring parts of the North-East.

Earlier, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria, Sule Ahmed Abdulaziz, said electricity demand in Gombe and communities served by the transmission station had outgrown its previous capacity.

He said the project involved installing the additional 300MVA transformer and replacing the existing 30MVA unit with a 100MVA transformer.

According to him, TCN awarded the project in June 2021, while construction was completed in June 2026.

The upgrades are expected to improve the capacity of the transmission network to accommodate growing electricity demand in Gombe and surrounding communities.

Keep the news with you

Read the latest stories and save articles in the Galaxy TV app.

Tags:
Kimberly Dirisu
Junior Digital Content & Communications Executive

Reporting for Galaxy TV from Lagos and Abuja, covering energy and national affairs across Nigeria and West Africa