Skip to content
Headlines
HomeEnergyFG inaugurates 520MVA transmission facilities in Gombe
Nov 19, 20261 min read

FG inaugurates 520MVA transmission facilities in Gombe

FG inaugurates 520MVA transmission facilities in Gombe
Galaxy TV · Energy desk · Lagos

The facilities comprise two 60MVA, 132/33kV transformers at Billiri substation and 300MVA and 100MVA transformers at Gombe transmission substation. The 300MVA transformer operates at 330/132kV, while the 100MVA unit operates at 132/33kV.

Story reading is not supported in this browser.

Share

The Federal Government has inaugurated transmission facilities with a combined transformer rating of 520MVA in Gombe State to strengthen electricity transmission and improve power supply.

The facilities comprise two 60MVA, 132/33kV transformers at Billiri substation and 300MVA and 100MVA transformers at Gombe transmission substation.

The 300MVA transformer operates at 330/132kV, while the 100MVA unit operates at 132/33kV.

Start tomorrow informed

Save your place for the morning brief. We’ll start emailing when delivery goes live.

Free. Confirm by email. Unsubscribe anytime.

The Minister of Power, Mr Joseph Tegbe, inaugurated the facilities on Thursday alongside TCN Managing Director, Mr Sule Abdulaziz.

Speaking in Billiri, Tegbe said the projects demonstrated the Federal Government’s commitment to addressing infrastructure gaps and strengthening the power sector.

He said the investments would support communities whose economic potential had been constrained by inadequate electricity infrastructure.

Tegbe said the Billiri substation would extend transmission capacity to Billiri, Numan in Adamawa State and neighbouring communities.

He said the intervention aligned with President Bola Tinubu’s Renewed Hope Agenda, which seeks to provide infrastructure supporting economic activities.

The minister said the facilities would strengthen electricity transmission across Gombe State and address suppressed demand within Jos Electricity Distribution Company’s franchise area.

He said the Federal Government was addressing longstanding transmission challenges through similar projects across the country.

“We cannot build a competitive economy on a transmission network that is perpetually struggling to meet future requirements,” he said.

Tegbe said the administration was rehabilitating critical assets, reinforcing strategic transmission corridors and removing bottlenecks affecting electricity delivery.

He said the investments aimed to improve grid reliability, unlock stranded capacity and support productive economic activities.

Abdulaziz commended the Federal Government, World Bank and Chris Ejik International Ltd. for funding and executing the Billiri substation project.

He said the substations would provide additional sources of bulk electricity supply and strengthen the transmission-distribution interface.

According to him, the facilities would improve the network’s capacity to meet existing and future electricity demand.

Abdulaziz urged residents of Billiri and Gombe to protect the substations and associated transmission infrastructure against vandalism and encroachment.

He warned that such activities could compromise public safety and undermine the projects’ intended benefits.

Gov. Inuwa Yahaya of Gombe State thanked President Tinubu for investments in the power sector to support economic growth.

Yahaya was represented by the Commissioner for Energy and Mineral Resources, Alhaji Sanusi Ahmad.

Ahmad said the transformers would help address critical transmission constraints and improve the national network’s operational flexibility.

Keep the news with you

Read the latest stories and save articles in the Galaxy TV app.

Tags:
Catherine Chinenye Igwe
Editor

Catherine Igwe is a Digital Journalist at Galaxy Television. She has over half a decade of experience in SEO content writing, digital marketing, and online publishing, creating engaging, search-optimised content for diverse audiences.