Former Minister of Power, Works and Housing, Babatunde Fashola, has defended the electricity sector’s performance under the late Muhammadu Buhari’s administration, saying more than 11 million Nigerians gained access to electricity for the first time during his tenure.
Fashola also disclosed that his ministry recovered 910 containers of stranded electricity equipment from Nigerian ports, insisting that the achievements demonstrated progress in the power sector despite persistent challenges.
The former Lagos State governor made the claims during an interview on Arise News Channel on Friday, where he discussed ways to address Nigeria’s electricity crisis.
Fashola, who served as power minister throughout Buhari’s administration, said the government had pursued incremental improvements rather than promising immediate stable and uninterrupted electricity supply.
“When I left the Ministry of Power in 2019, people who followed our performance would tell you that it was getting better,” he said.
He added that more than 11 million people were connected to electricity supply for the first time during his tenure.
Fashola attributed some of the sector’s challenges to a lack of understanding of the responsibilities created by the 2013 privatisation exercise, which transferred electricity generation and distribution to private operators while the Federal Government retained control of transmission.
Start tomorrow informed
Save your place for the morning brief. We’ll start emailing when delivery goes live.
Free. Confirm by email. Unsubscribe anytime.
He said the workforce responsible for operating the generation and distribution companies had fallen from about 52,000 to 776 following the privatisation.
The former minister argued that electricity distribution and generation companies should be held accountable for poor service delivery, noting that consumers paid private service providers rather than the government.
“Who is collecting payment for electricity? Is it government or your service provider?” he asked, urging the media to invite the companies’ chief executives to explain the persistent power problems.
Fashola, however, said he was not blaming the operators but highlighting the need to understand the structure of the sector.
He also welcomed the decentralisation of electricity generation, transmission and distribution under President Bola Tinubu, saying it would allow states to develop their own power infrastructure.
According to him, greater participation by state governments could reduce dependence on the Federal Government and expand electricity supply across the country.
“If each state begins to generate its own power, we are on our way,” he said.
On electricity equipment reportedly trapped at Nigerian ports, Fashola recalled that he inherited more than 1,000 containers of stranded materials when he assumed office.
He said a meeting chaired by former Vice-President Yemi Osinbajo, involving warehouse operators and shipping companies, was convened to address the problem.
Fashola said his ministry eventually recovered 910 containers and deployed the equipment to locations including Kuje, Katampe, Isolo and Kurudu to strengthen the national grid.
He also reacted to reports that more than 800 containers of electricity equipment were currently stranded at the ports, suggesting that they represented fresh investments in the sector.
“It's not an old 800, it's a new 800,” he said.
The former minister attributed the earlier delays to changes in equipment prices, inadequate budgetary provisions and contractors’ inability to execute projects under the original contract terms.
He argued that the public procurement system contributed to delays by limiting initial payments to contractors, sometimes to 15 per cent of contract sums.
According to him, higher initial payments could have enabled contractors to import equipment before international prices changed.
“If those contractors had been paid up to 70 per cent, they would have imported the equipment,” he said.
Fashola maintained that improving electricity supply required better procurement processes, accountability from private operators and increased participation by state governments.